Panama Team
Project details
The Panama team is working in Valle Escondido to provide clean water access to the local community! To do this we have been designing and constructing a new water distribution system. This reconstruction has been split into two separate phases.
The first of which the team recently completed in September 2024! During our implementation trip we:
-
Added 40,000L of water storage
-
Replaced and buried 4” mainline pipe
-
Added inline chlorine water treatment
The community is currently adding the individual connections to the mainline. They will also be constructing a spring box to protect the water source feeding the distribution system. During our next implementation trip we aim to:
-
Add an additional 30,000L of water storage. This will ensure the system has a day's worth of water for the community 20 years into the future
-
Protect and develop more of their springs which will most likely entail building more spring boxes
-
Replacing and burying the 2” mainline piping from the springs to the tanks
After completing these two phases the entire community will have reliable access to clean water. The team will continue monitoring, supporting, and working with the community to ensure the success of the project.
Project History
Start of Project
2020
Floating Doctors reached out to the UCSB EWB student chapter.
Assessment Trip
March 2022
Our team traveled to Valle Escondido to meet the community and conduct a site assessment to better understand how we can effectively and sustainably provide clean water to the community. After spending a week with the community, conducting oral surveys about community illness and water needs, as well as evaluating available water sources (quantity and quality via broad sampling campaigns), we found the community to be greatly struggling to supply enough water to all its members. Many members have to drink from the small stream pool where they also bathe, wash clothes, and which is frequented by animals. We observed high concentrations of bacteria in the streams and other sources used by the community.
Design Phase
2022-2024
After assessing the water issues of the community, we determined the best solution was to a reconstruct their water distribution system. We modeled the system based on a topographical survey of the community. Then we calculated the proper pipe sizing and added air valves and blowoff valves according to the hydraulic grade line. This ensured the system would have sufficient flow unobstructed by head loss, trapped air, or sediment.
Implementation Trip
Phase 1
September 2024
During this implementation, we constructed phase 1 of the project. We worked alongside the community and Floating Doctors to build over a kilometer of pipe, install the new tanks, and add chlorination within 2 weeks.